Project Description

Client

Confidential.

Work performed

Adenfi has performed technical and financial due-diligences in the acquisition process. An energy yield assessment has been audited and Adenfi has contacted some potential PPA contractors in Spain. Input of the business model has been audited in relation to the technical diligences and construction agreement. The project construction began in January 2020 and the solar plant is expected to be operational by September 2020.

Localisation
Caceres, Extremadura, Spain

1 PV Plant

Capacity
300 MWp

822 hectares
of land